How long does a house extension take?

For a typical 25–30 m² single-storey rear extension needing full planning, allow about 8–9 months (35–40 weeks) from first design meeting to completion. Only around three of those months are on site.

PhaseTypical weeksWhat happens
Survey and design to planning6–8Measured survey, concept and planning drawings
Planning: validation and decisionabout 138-week statutory target, but allow about 13 weeks in practice
Technical design and tender4 (8 with party wall)Building Regulations drawings, structural calculations, quotes; party wall notices if attached
Build on site12–14For about 30 m² of new extension; more for larger or double-storey work
Totalabout 35–40

What changes the timeline

Practice-based guide. These are typical durations, not guarantees. Your Architect and builder will set the programme for your project.