How long does a house extension take?
For a typical 25–30 m² single-storey rear extension needing full planning, allow about 8–9 months (35–40 weeks) from first design meeting to completion. Only around three of those months are on site.
| Phase | Typical weeks | What happens |
|---|---|---|
| Survey and design to planning | 6–8 | Measured survey, concept and planning drawings |
| Planning: validation and decision | about 13 | 8-week statutory target, but allow about 13 weeks in practice |
| Technical design and tender | 4 (8 with party wall) | Building Regulations drawings, structural calculations, quotes; party wall notices if attached |
| Build on site | 12–14 | For about 30 m² of new extension; more for larger or double-storey work |
| Total | about 35–40 |
What changes the timeline
- Planning route: a Lawful Development Certificate or prior approval is usually quicker; householder planning is the longest.
- Party wall: notices and awards add about a month on attached houses.
- Size and type: double-storey extensions typically take 18–22 weeks on site; dormer lofts 10–12.
- Renovating existing rooms at the same time: allow about one extra week on site for every 15 m² of existing rooms refurbished alongside the extension.
- Builder availability: good builders are often booked months ahead, so start talking to them during planning.
Practice-based guide. These are typical durations, not guarantees. Your Architect and builder will set the programme for your project.